A uPVC window is only as good as its installation. This is the process our team and partner fabricators follow, and the support that continues after handover.
Site survey
Surveys begin during the plastering stage. Height, width and diagonals of every opening are measured with the site engineers.
Design confirmation
Window sizes, designs and placements are confirmed with the engineer before fabrication.
Positioning
Windows are positioned exactly using tube level and plumb level so frames are true and square.
Anchoring
Frames are screwed with hanger fastener screws using hammering machines so they hold strongly to the walls.
Sealing
Perimeters are sealed with silicone sealant for tight packing without gaps. Protective tape is removed after installation.
Our relationship begins after installation.
We understand the importance of after-sales service and its impact on long-term relationships. Our experienced service team handles post-sales queries promptly — from hardware adjustment and gasket replacement to technical guidance for fabricators.
Raise a service request
Getting the site ready
Most installation problems start before the installers arrive. This is what the opening should look like.
- Openings plastered, square and to the agreed size, with diagonals checked
- Sills finished with an outward slope and drip groove
- Chajjas and sunshades complete so water falls clear of the frame head
- Finished floor level confirmed for door frames
- Wet trades complete in the room, or windows protected from slurry
- Clear access and safe working platforms for upper floors
What good installation looks like
The practices we train fabricators to follow on every site.
| Stage | Standard | Why it matters |
|---|---|---|
| Positioning | Plumb, level and square, checked with level and diagonals | Sashes run smoothly and seal evenly |
| Packing | Packers under fixing points and at corners | Frame doesn’t twist when screws are tightened |
| Anchoring | Frame fasteners into masonry at regular centres | Resists wind load and daily use |
| Cavity | Gap between frame and wall fully filled | Stops air, water and noise paths |
| Sealing | Continuous silicone outside and inside | The main defence against leaks |
| Drainage | Slots clear and opening to the outside | Water in the track drains away |
| Adjustment | Hardware set for smooth operation and even gasket pressure | Easy use, tight seal |
| Finishing | Protective tape removed, frames and glass cleaned | Tape bakes on if left in the sun |
Care and service
uPVC windows need very little, but a few minutes of care a few times a year keeps them running like new: clean tracks and drainage, wipe gaskets, lubricate hardware lightly, and do a quick check before the monsoon. Our maintenance guide sets out a simple yearly routine.
If something isn’t right — a sash dropping, a lock not pulling tight, water entering during rain — contact the fabricator who installed the window first. Most issues are quick adjustments. Fabricators using Fenplast profiles can call our technical desk for guidance on profiles, reinforcement and fabrication.
Installation questions
When should uPVC windows be installed during construction?
Site surveys start during plastering. Final installation is best done after wet trades and before final painting, with protective tape removed immediately afterwards.
How long does installation take?
A typical apartment can be installed in a day or two once frames are fabricated; larger projects are scheduled floor by floor.
Who seals the gap between the window and the wall?
The installation team fills the cavity and seals the perimeter with silicone inside and out. It’s a critical step for preventing leaks.
What should I check at handover?
Every sash opens, closes and locks smoothly; frames are plumb and square; perimeter silicone is continuous; drainage is clear; protective tape is removed; glass is undamaged.